A Katsina state government project verification committee has uncovered a total 712 projects believed to have been executed and paid by the administration, 32 of them were found not executed, 6 abandoned just as 12 others not documented.
The
total 712 projects are valued at about N8.4b and were said to be
executed by six MDA's; Ministry of Education and Health, Science and
Technical Board, State Universal Basic Education, Universal Basic
Education commission, and the Sustainable Development Goals SDG's
Presenting,
the report, the acting chairman of the committee, Umar Rigoji said 581
of the projects have been executed and completed satisfactorily, 52
poorly and partially executed while 26 are ongoing.
He
said, each project site was visited and fully assessed before reaching a
verdict adding that 'for those poorly or partially executed, unexecuted
and or abandoned government may look at the terms and conditions
governing them and seek for legal redress'
In
his remarks, governor Aminu Masari commended the committee for the work
and assured the consultants and staff at the MDA's must be made
accountable saying that the administration has been receiving complains
especially on the social media which prompted the constitution of the
independent verification committee.